All the NRG Project News
 
NRG 1.500 is already delivering energy to the net   NRG 1.500 mill has already started generating energy at its 100 per cent of power capability (concluded
last July 31st), with highly satisfactory test results before arise expectations.... read more
 
NRG Patagonia will be present
in Brazil Windpower 2010
  During 31st August, 1st and 2nd September Brazil Windpower 2010 exposition , in Rio de Janeiro , Brazil will
take place. It is the main pan American latin event of the eolic area, organized by the Industrial... read more
 
NRG Patagonia finished
the installation of its first
equipment NRG 1.500
  NRG Patagonia finished the installation of its first equipment NRG 1.500, located in the area of El Tordillo. This
task was successful, and according to the projections done. These jobs demanded an exact logistic... read more
 
Transfer of the tower
to the mounting site
  On Sunday March 28, 2010, another important step in the NRG Patagonia Project was fulfilled with the transfer
of the three lengths that make up the tower, which will have a total height of 70 meters and a... read more
 
NRG 1.500 Aerogenerator assembly completion in workshop   The regional company NRG PATAGONIA SA completed the assembly in workshop of its NRG 1500 aerogenerator,
an eolic generator with a nominal power of 1,500 Kilowatts, built under technology and design... read more
 
German technicians verified
the windmill components
  In the framework of the verification and test in bank tasks developed, NRG PATAGONIA received during the first week of December 2009 the visit of technicians from Denmark and Germany, one from Mita Tekni... read more
 
ENARSA inspections   As part of periodical inspections in charge of professionals from ENARSA ( Argentinian Energy S.A.) new building controls on NRG 1500 were done in the local workshop, and at the same time the verification done... read more
 
The Mayor of Comodoro
Rivadavia valued NRG
Patagonia diversification
  On Thursday December 24th , the Mayor Martín Buzzi visited the workshop where the step of assembly of NRG 1500 was finished, specially invited by the president of NRG PATAGONIA, Mr. Carlos Otamendi. It... read more
 
Concreting of foundations   According to the works schedule planned for the development of the project related to the construction of the
1,5 Mw NRG aerogenerator, the concreting of foundations was materialized last June, 25th, with... read more
 
Flange Assembly   Another one of the preliminary jobs performed for the mounting of the tower, that is 70 meters high, was the
tie down flange in the concrete foundation, which has left the location ready for the subsequent... read more
 
 
  NRG 1.500 is already delivering energy to the net    NRG Patagonia will be present in Brazil Windpower 2010    NRG Patagonia finished the installation of its first equipment NRG 1.500     Transfer of the tower to the mounting site     NRG 1.500 Aerogenerator assembly completion in workshop     German technicians verified the windmill components     ENARSA inspections     The Mayor of Comodoro Rivadavia valued NRG Patagonia diversification     All the NRG Project News     News from the sector
 
     
 
 
 
News | Gallery: Videos | Images | Who we are | Contact | What we do | Join us | Where we are | Activities | NRG products
© 2009 // NRG Patagonia - All rights reserved